| Installation
Guide : |
|
|
Drill a bore of the required
size and depth in the ground using suitable
boring technique.
|
|
|
Ensure that sufficient
screen and plain casing pipes have been
made available based on water source.
|
|
|
Select appropriate type
of pipes (CM or CS) to avoid collapse in
a bore.
|
|
|
Ensure that every casing
pipe of be installed is provided with rubber
seal (Ring) at threads.
|
|
|
Always use bottom cap with sand traps.
|
|
|
Fit "C" Clamp
below the bell end of the pipe and lower
assembly down in the bore with the help
of chain pulley block.
|
|
|
After lowering the pipe
up to the clamp level, tight the second
pipe gently with the lowered pipe
|
|
|
Use chain wrench for proper
jointing but do not over tight.
|
|
|
Fix next clamp below bell
end of the second pipe and connect the chain
pulley with clamp.
|
|
|
Remove the clamp of lower
pipe and start lowering further.
|
|
|
Repeat the jointing method till the required
depth of bore well is reached.
|
|
|
Fill the gravel between pipe and bore hole.
|
| |
|
Dimentions of uPVC Casing Pipes - CS
As per IS : 12818-1992
(Suitable for wells depth up to 80 meter)
|